Contracts for Ukrainian Nuclear Power Plants
From 2015 until 2023, I&C Energo a.s. participates in the program “Modernization and Safety Improvement of Ukrainian Nuclear Power Plants”. As part of this program, which is fully financed by the European Bank for Reconstruction and Development (EBRD), I&C Energo a.s. implemented the following projects:
- Supply of low-voltage DC switchboards for emergency power supply to all four Ukrainian nuclear power plants, i.e. to the Zaporizhzhia NPP, the South Ukraine NPP, the Khmelnytskyi NPP and the Rivne NPP;
- Supply of low-voltage switchboards for substations of internal loads, protective relays and microprocessor-based generator-transformer block automation, and blocks of switchboard power cabinets for emergency power supply to Units 3, 4, 5, and 6 of the Zaporizhzhia Nuclear Power Plant;
- Supply of low-voltage AC switchboards for complete transformer substations of internal loads for Unit 4 of the Roven Nuclear Power Plant.
The complete delivery of low-voltage switchboards amounted to 226 pcs (1,981 cabinets); the delivery further included 156 protection enclosures and 156 blocks of switchboard power cabinets. All supplied switchboards, protection enclosures and blocks of power supply boxes were manufactured by I&С Energo. The scope of supply was completed by 146 dry-type distribution transformers 400/1000 kVA.